  1. 1What the work isA new installation, an addition or an alteration, ticked across the top.
  2. 2Next inspectionYou enter the recommended interval in months. The date is worked out when the certificate is issued.
  3. 3Supply and earthingEarthing arrangement, voltage, prospective fault current and external earth fault loop impedance.
  4. 4DeclarationsDesign, construction, and inspection and testing. One signatory can sign for all three.
  5. 5Serial numberEIC, the year and your company's running number.

A sample with made-up details: a replacement consumer unit with five circuits. A certificate carries DRAFT until it is issued.

The rules for an EIC

What it certifies

That new work was designed, built, inspected and tested to the wiring regulations. The IET publishes the model form.

IET: BS 7671 model forms ↗

When the work is notifiable

In England a new circuit, a replacement consumer unit and work in a special location must be notified to building control.

Building Regulations 2010, regulation 12 ↗

The standard

BS 7671:2018 with Amendment 4:2026, published 15 April 2026. The previous version is withdrawn on 15 October 2026.

IET: Amendment 4:2026 published ↗

What is on the form

Description and extent
What the work is and which parts of the installation the certificate covers.
Declarations and signatories
Design, construction, and inspection and testing, with any departures from the regulations.
Supply and earthing
Supply characteristics, earthing, bonding and the main switch.
Consumer unit
The board, its protective devices, surge protection and the test instruments used.
Schedule of inspections
Fourteen items. Each takes a tick or not applicable.
Circuits and test results
A row for each circuit, from the protective device to the measured values.

What the form does for you

  • Works out the next inspection date from the interval you enter.
  • Will not issue until every item on the schedule of inspections has a tick or not applicable.
  • Refuses incorrect polarity on a circuit: it cannot be certified on an installation certificate.
  • One tick makes you the signatory for design, construction and inspection, or each can be named separately.
  • Fills in today's date, the customer, the address and your company details when the draft is started.

Filling it in on the phone

The same form is in the web app, where the circuit schedule has the width of a desk screen.

The installation certificate on a phone: four sections, each marked to do or with its circuit count
The certificate's four sections, with what is done and what is left.
The first section of the installation certificate, asking whether the work is new, an addition or an alteration
The first section: what the work is and what it covers.
More of the first section, with Back, Preview and Next
Further down the same section. Preview shows the PDF so far.

After it is issued

A signed PDF

Digitally signed when issued. Changing the file breaks the signature.

A QR code and an online copy

The QR code on the certificate opens its online copy. No account is needed to read it.

Serial number

EIC-2600076: the code, the year and your company's running number.

Send it

Share the PDF or copy the link from the phone. Add it to the job's invoice and it goes out with the invoice email.

On the certificates register

Listed with the date the next inspection is recommended. It reads Due from the day that date arrives.

Your enrolment

A NICEIC Approved Contractor or NAPIT mark is printed when your enrolment number is on file.

How certificates work in Jobivo

The other electrical forms

Nine more, started from the same job.

Electrical condition reportEICRThe condition of an existing installation, with coded observations.
Minor works certificateAdditions and alterations that do not add a circuit.
PAT testing reportOne row per appliance, with totals counted from the rows.
Electrical danger noticeFor a dangerous condition found on site. Signed by the person responsible, issued from the web app.
Emergency lighting completion certificateA new, altered or extended installation.
Emergency lighting existing site certificateAn existing installation assessed against a 35-item checklist.
Emergency lighting periodic test certificateThe periodic test, luminaire by luminaire.
Emergency lighting service certificateWhat was done on a maintenance visit.
Emergency lighting luminaire listThe list of fittings the other emergency lighting forms refer to.

All electrical certificates

Try Jobivo free for 14 days.

No card required. Set up in minutes.

An EIC or a minor works certificate

An installation certificate is for a new installation, a new circuit or a replacement consumer unit. A change to an existing circuit that adds no new circuit, such as an extra socket, goes on a Minor works certificate. Both are started from the same job.

Common questions

When do I need an EIC?

For a new installation, a new circuit or a replacement consumer unit. Work that only alters an existing circuit goes on a Minor works certificate.

Is the form on the current wiring regulations?

Yes. It follows the model form for BS 7671:2018 with Amendment 4:2026.

Does the certificate notify building control?

No. Notification is done through your competent person scheme or the local authority. The certificate is the record of the work.

Do I need to be registered with a scheme to issue one?

Jobivo does not require a scheme number to issue an electrical form. If your NICEIC or NAPIT enrolment is on file, the mark is printed on the certificate.

Last updated